Skip to content

Project Management MCQ Questions

0
Answered
0
Correct
0%
Accuracy
Q51 Easy

A burndown chart is used for which of the following purposes?

To estimate team member energy level.
To show the organizational hierarchy of the project.
To visualize schedule progress.
To estimate remaining cost.
Q52 Easy

This action reduces the probability and/or impact of an adverse risk event to below an acceptable level.

Risk planning
Risk analysis
Risk prevention
Risk mitigation
Q53 Easy

In the schedule performance Index the earned value to date divided by the _______ of work scheduled to be performed (EV/PV). This value allows us to calculate the project’s schedule to completion

PV
Time
AC
Ev
Q54 Easy

The team is working on the project and regular communication is happening between the project manager, the team, and the client. Which project phase are you in?

Project execution
Project initiation
Project control
Project planning
Q55 Easy

In a pert/cpm chart, each task has all of the following except a(n) ____.

Reference to successor tasks
ID
Name
Duration
Q56 Easy

A project manager?s planning _____.

The start of user training
Conversion of system data
Completion of interviews
Includes informing management, users, and the project team about the progress of the projectproject cost, scope, and time
Q57 Easy

A _____ consists of horizontal bars, connected with arrows that indicate task dependencies.

Wireframe
Scatter chart
Viewport
Gantt chart.
Q58 Easy

The quantity of time that will elapse from the start of an activity to its end is called what?

Work required
Duration
Effort
Time required
Q59 Easy

Which of the following is involved with fast tracking a schedule?

Bringing in additional project management to oversee the schedule
Setting up incentives to motivate the team to work faster
Arranging some project activities to happen concurrently, rather than sequentially
Reassigning activities that can be done faster through outsourcing
Q60 Easy

What is a WBS input?

Overhead costs related to an activity.
Items needed before an activity can be done.
The documents needed to run a WBS meeting.
Time estimates for an activity.
Q61 Easy

________ is reducing the probability and/or impact of an adverse risk event to below an acceptable level.

Risk mitigation
Risk prevention
Risk planning
Risk analysis
Q62 Easy

In the ______ stage, the team members decide what they expect to achieve with the project.

Planning
Management
Execution
Conceptualization
Q63 Easy

Performing quality assurance is a subprocess of the _____ process of project quality management

Executing
Initiating
Closing
Monitoring and controlling
Q64 Easy

The ______ should include all costs relevant to the project, the most important of which are personnel costs, equipment and materials, and the project overhead.

Planned value
Earned value
Cost performance index
Time-phased budget
Q65 Easy

The cumulative total cost of completing the project’s work packages is known as

Actual Cost of Work Performed
Cost Performance Index
Schedule Performance Index
Q66 Easy

Story Points is a term used in Agile PM to define the relative cost and complexity of each task; also known as __________ .

Complexity points
Story
Velocity
None of these
Q67 Easy

_______ is the best estimate of completion time for an activity, given normal conditions.

Expected activity completion time
Pessimistic completion time
Optimistic completion time
Most likely completion time
Q68 Easy

What is the process of administering actionable tasks called?

Representation
Delegation
Quantification
Relaying
Q69 Easy

The _____ should list and describe all of the deliverables required for the project.

Project charter
Scope statement
WBS
Gantt chart
Q70 Easy

Which of the following is NOT a source selection criteria used in contract procurement?

technical capability
open change requests
understanding of need
cost
Q71 Easy

Which of the following refers to the cumulative total cost of completing the project’s work packages?

Earned value
Planned value
Cost performance index
Actual cost of work performed
Q72 Easy

_______ is giving the customer more than what was required.

Performance
Quality
Earned value
Gold-plating
Q73 Easy

A ____ path includes all tasks that are vital to the project schedule.

Vital
Baseline
Critical
Foundational
Q74 Easy

______ is the earned value minus the actual cost of work performed.

Cost performance index
Cost variance
Schedule variance
Earned value
Q75 Easy

Probability of Completing a Project by a Given Time Use the standard normal equation to find Z .

True
False
Q76 Easy

EF is Stands for (Operation Management)

Ejection Fraction
Entity Framework
Energy Factor
Early Finish Time
Q77 Easy

The most common approach for closing or terminating a project is through _______.

Addition.
Extinction.
Integration.
Starvation.
Q78 Easy

Microsoft claims that the microsoft project software can _____.

Linking risks with specific vendors
Assign ownership of risks
Eliminating risk
Preventing fraud
Q79 Easy

______ is the latest possible date an activity can be completed without delaying the project’s completion.

Late finish time
Early start time
Late start time
Early finish time
Q80 Easy

_________ and the path arrows to represent the sequencing of tasks from node to node through the network

Individual project activity
Grouped project activity
Both a & b
None of these
Q81 Easy

The _______ is the time to complete the activity if everything goes according to plan.

Critical path
Slack time
Optimistic completion time
Most likely completion time
Q82 Easy

Tasks in a wbs that are decomposed into smaller tasks are called _____ tasks.

Total slack
Network diagram
Late start date
Summary
Q83 Easy

Free software for small businesses with relatively less complex projects is known as _____ .

Most Likely Completion Time
Open Source Software
Operational Risks
None of these
Q84 Easy

activities that comprise the deliverables of a project is known as

West Bank Structure
Weekly Bulletin Structure
Work Packages
None of these
Q85 Easy

More rework in a project means:

Poor project management
Poor team management
Poor governance
All of these
Q86 Easy

____ dependencies involve relationships between project and non-project activities.

Mandatory
External
Discretionary
Internal
Q87 Easy

Prime role of a Project Manager is:

Risk mitigation
Crisis management
All of these
Project closure
Q88 Easy

Which of the following is NOT an interpersonal skill a project manager should use when managing stakeholders expectations?

Active listening
Building trust
Resolving conflict
Managing change requests
Q89 Easy

Subdividing the project deliverables into smaller pieces is known as _____.

Variance
Benchmarking
Prototyping
Decomposition
Q90 Easy

A diagram that illustrates how activities should best be sequenced is known as

Activity Network
Activity on Arrow
Activity on Node
None of these
Q91 Easy

_____ involves doing whatever you can to make sure the positive risk happens.

Risk transference
Risk avoidance
Risk mitigation
Risk exploitation
Q92 Easy

Customer Requirement is captured during:

Project execution phase
After the project is completed
Project planning phase
Project initiation phase
Q93 Easy

______ is the manufacturing or assembling of materials to create the product or service.

Procurement
Fabrication
Innovation
Production
Q94 Easy

A ______ is a unique venture with a beginning and end, conducted by people to meet established goals within certain cost, schedule, and quality parameters.

Process
Project
Product development
Quality management
Q95 Easy

In organizational culture, control refers to _____.

The degree to which employees are encouraged to be aggressive, innovative, and risk seeking.
The degree to which management focuses on outcomes rather than on techniques and processes
The degree to which the organization monitors and responds to changes in the external environment
The degree to which rules, policies, and direct supervision are used to oversee employee behavior
Q96 Easy

“Unexpected events that can cause missed completion times” best describes _______.

Project risks
Cost risks
External risks
Schedule risks
Q97 Easy

What is involved with fast tracking a schedule?

Setting up incentives to motivate the team to work faster.
Arranging some project activities to happen concurrently, rather than sequentially.
Reassigning activities that can be done faster through outsourcing.
Bringing in additional project management to oversee the schedule.
Q98 Easy

Which of the following should oversee the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information??

Project Communications Management
Project Cost Management
Performance Management
Project Quality Management
Q99 Easy

______ works best when you can be reasonably certain of how long the project’s activities are likely to take.

Program evaluation and review technique
Critical path method
Benchmarking
Time management
Q100 Easy

Software designed to track a project’s progress is known as ______.

Project Management Software,
Project Risk Management
Risk Mitigation Plans
None of these
Showing 100 of 388 questions

Teachers: using these Project Management questions with a class? Tell us about your class.

Report a mistake

What's wrong?