Project Management MCQ Questions

0
Answered
0
Correct
0%
Accuracy
Q101 Easy

In a(n) _____ organizational structure, project managers have little or no authority.

Functional
Weak matrix.
Balanced matrix.
Projectized
Q102 Easy

Three general classifications of organizational structures are _____, project, and matrix.

Champion
Symbolic
Functional
Structural
Q103 Easy

If you want to evaluate how much work effort remains on the project, what measure are you most likely to use?

PMBOK
BOM
OBS
ETC
Q104 Easy

_______ is the formal process to review, approve, and manage changes to project deliverables, documents, and the project management plan throughout the project.

Performance control
Integrated Change Control
Performance plan
Plan management
Q105 Easy

Scope Creep is a situation in which project specifications are continually modified or improved as ________ or new technical solutions become possible

New ideas emerge
Old ideas emerge
Ideas never emerge
None of these
Q106 Easy

What is scope creep?

A slower than desired progress in completing the scope of a project.
Features and deliverables not agreed to in the original plan.
That slimy guy with glasses.
When a client repeatedly adds new features during planning.
Q107 Easy

Risks that are mostly within company control, such as cost overruns by suppliers and subcontractors is known as _____ .

Cost Risks
Crash Cost
Crash Time
Critical Activities
Q108 Easy

Generally, in what project phase is risk and opportunity greater than the amount at stake?

Closing phase
Monitoring and Controlling Phase
Executing phase
Planning phase
Q109 Easy

_________ ia an Agile concept in which the iterations are extremely short, so each iteration only contains a few tasks and feedback from product owners is rapid and frequent

Extreme Programming (XP)
Burndown Chart
Function Point Analysis
None of these
Q110 Easy

______ is the cost estimate of the budgeted resources scheduled across the project’s life cycle.

Earned value
Planned value
Cost performance index
Time-phased budget
Q111 Easy

Projectized refers to what?

An organization that focuses on obtaining, planning, and completing projects.
An organization that enters the majority of its work into project management systems.
Project teams managed in waterfall methodologies as opposed to agile methodologies.
An organizational structure where the team members report directly to a project manager.
Q112 Easy

_______ is free software for small businesses with relatively less complex projects.

Project management software
Open source software
Cloud computing
Cloud-based project management solution
Q113 Easy

_______ consists of all the processes that ensure that the work necessary, and only the work necessary, to successfully complete the project has been defined.

Project Scope Management
Change Management
Performance Management
Project Planning
Q114 Easy

_____ involves prioritizing risks based on their probability and impact of occurrence.

Performing qualitative risk analysis
Identifying risks
Planning risk responses
Performing quantitative risk analysis
Q115 Easy

Which of these IS a valid earned value rule?

COCOMO
S-curve
Agile sprint
25/75
Q116 Easy

A client has added tasks to a contracted project without full disclosure. What is this called?

Scope Drip
Screening
Blind Screening
Scope Creep
Q117 Easy

What does a Project Lifecycle consist of?

Checking how many cycles there are in a project
Defining project in a cyclic manner
Writing a report on life of a project
A logical sequence of project phases comprising of associated activities
Q118 Easy

________ is a provision, usually time or money, to mitigate cost and/or schedule risk.

Reserve
Planning
Hold back funds
Risk mitigation
Q119 Easy

Industry standard tools for scheduling and project management include pert, wbs, and ________.

External integration tools
Pert charts
Formal planning tools and formal control tools
Gantt charts
Q120 Easy

A task that represents several activities is known as a _____.

Task name
Task ID
Task review
Task group.
Q121 Easy

_______ is the processes involved in estimating, budgeting, and controlling costs so the project can be completed within the approved budget.

Project Cost Management
Project Planning
Project Quality Management
Performance Management
Q122 Easy

You are monitoring the schedule progress and evaluating budget. You see a trend of going over budget and are having conversations to correct the issue. Which project phase are you in?

Project initiation
Project control
Project execution
Project planning
Q123 Easy

The _____ line for any e-mail messages you write should clearly state the intention of the e-mail.

To
From
Subject
Cc
Q124 Easy

Which of the following refers to the earned value to date divided by the planned value of work scheduled to be performed?

Earned value
Schedule performance index
Cost performance index
Planned value
Q125 Easy

S-curve is typical shape of a project’s status graphically Plotted against_______

Time
Value
Strategies
None of these
Q126 Easy

The main purpose of the planning phase in a project is to ________.

Set up the project scope and initial budget
Accomplish the project tasks effectively
Determine who will do what and by when
Decide if the task status reporting process is needed or not
Q127 Easy

What is the main responsibility of the Steering Committe during Project Execution?

Sit back and relax, watch the project execute.
Investigate the possibilities for enlargement of financial budget for future problems?
Making clear and timely decisions
Discuss with all stakeholders, that the Projectmanager communicates with, about the status of the Project
Q128 Easy

When is a WBS used?

When contrasting final deliverables to original contract.
When documenting a team member change.
When cancelling vendor agreements.
When identifying activities needed to create deliverables.
Q129 Easy

Which one of the following is NOT one of the four P's that effective software project management focuses on?

Project
Perspective
Process
People
Q130 Easy

The process of converting a project’s goals into a logical method for completing them on time is known as

Project Management
Project Risk
Project Scheduling
Risk Management
Q131 Easy

What is a project manager called when using scrum methodologies?

Product Manager
Program Manager
Scrum Master
Project Manager
Q132 Easy

In the ________ stage of what is a project?, a major portion of the actual project work performed.

Planning
Defining
Closing
Executing
Q133 Easy

Which is a technique used to determine whether particular work can be accomplished by the project team or must be purchased from an outside source?

Project planning
Time-and-materials contract
Procurement analysis
Make-or-buy analysis
Q134 Easy

The point of planning is to ______.

Come up with one idea
Understand whats needs to be done
Stick to the script
Finish quickly
Q135 Easy

Which groups are included as project stakeholders?

Project team
All of these
Client contacts and management
Team supervisors
Q136 Easy

Which of the following consists of all the processes that ensure that only the work absolutely necessary to successfully complete the project has been defined?

Project Planning
Project Scope Management
Change Management
Performance Management
Q137 Easy

_____ refers to matching certain behaviors of the other person.

Teamwork
Recognition
Mirroring
Authority
Q138 Easy

Teams can be broadly classified as either ____.

Functional or cross-functional
Specific ability tests
Conduct a job analysis
Quid pro quo sexual harassment
Q139 Easy

A pump jack scaffold must be fitted with two ______ gripping mechanisms to prevent slippage.

Positive
Negative
Peculiar
Consisted
Q140 Easy

_______ is the shortest possible time for activity completion.

PERT
Project crashing
Optimistic completion time
Crash time
Q141 Easy

____ dependencies are inherent in the nature of the work being performed on a project.

Mandatory
External
Discretionary
Internal
Q142 Easy

_______ is a formal approved document that defines how a project is executed, monitored and controlled, and closed.

Performance Plan
Project Runner
Project Management Plan
Change Management Plan
Q143 Easy

_____ can be classified as internal to the organization or external.

Project Stakeholders
Investor
Company owner
None of these
Q144 Easy

On a pert chart, an arrow from "activity d" to "activity e" indicates that _______.

Having your lawn cut by the​ neighbor's son
You get a manicure and pedicure before an important event.
Activity D must be completed before Activity E can start
ISO 9000
Q145 Easy

A(n) _____ on a project is a significant event that normally has no duration.

Milestone
Activity attribute
Activity sequence
Schedule baseline
Q146 Easy

The first step in the creation of a pert/cpm chart is to ____.

Determine the logical order of project tasks
Identify the graphical planning aids to use
Identify all the project tasks
Determine the status of all tasks
Q147 Easy

Critical Path the sequence of activities in a network that defines the overall length of the project

True
False
Q148 Easy

Project closes with:

Project review
Product development
Product demo
Project closing declaration by project team
Q149 Easy

Earned Value is the real budgeted cost, or “value,” of the work actually performed to date.

True
False
Q150 Easy

_______ is the expected total cost of the project at completion.

Actual Cost (AC)
Total cost estimate
Estimated Cost at Completion (EAC)
Budget at Completion (BAC)
Showing 150 of 388 questions